Georgia – Pacific OSB Plant Demolition

do you have a construction project we can help with?

Georgia – Pacific, OSB Plant Demolition

Target completed demolition of 2 log cranes; 2 tree de-barkers; numerous conveyor systems resin, and wax tanks; 2 wastewater treatment systems; 3 RTO emission systems; combustible wood dust burning furnaces and storage
silos; an electrostatic precipitator, filtration baghouses, thermal/hydraulic oil piping, and a press that weighed over 1,000,000 pounds in a 40-foot pit.

  • Developed work plans including demolition plans, HASP, AHAs, and abatement and waste management plans.
  • Completed the project within six months, 30 days before the initially scheduled date
  • Recycled 5,000,000 pounds of metals, 8,500 gallons of recycled oils, 17,300 gallons of treated oily water, 304 tons of C&D debris and removed 100 tons of sludge.
  • Self-performed 88% of the total cost of this project involving dozens of various types of facilities across a 32-acre site, requiring efficient coordination and sequencing of crews and heavy equipment

Project Details

Location of Project

Grenada, MS

Awarded

11/10/2020

Completed

05/14/2021

Contract Value

$4,100,000

REFERENCE

Michael Hassett, PE
Georgia-Pacific
113 Peachtree St.
Atlanta, GA 30303
404.884.3236
Mike.Hassett@gapac.com

Project Gallery

Committed to an injury-free workplace

We are unwavering in our dedication to ensure zero injuries at every job site. To do this, we follow strict safety guidelines and hire skilled contractors to work on our projects. Staying committed to operating an injury-free workplace is the right choice and the only choice.

Let’s talk about your project.

Only takes a few seconds!