MCAS Cherry Point Building Demolition, Site P199

do you have a construction project we can help with?

MCAS Cherry Point, NC

Target conducted ACM/ORM abatement and removal of 14 facilities totaling 275,000 SF, including structures, slabs, and abandoned utilities to five feet outside of the building’s perimeter.

  • Developed work plans and provided site supervision, asbestos abatement, ORM removal, demolition, recycling/waste disposal, and site restoration
  • Submitted permits to NC DHHS and NC DPH for ACM abatement of over 110,000 SF of friable and non-friable materials, lead in demolition, and PCB/mercury disposal.
  • Recycled 2,975 tons of C&D, steel, and ORM and 60,296 CY of concrete to achieve 60% waste diversion goal.
  • Provided site restoration to ensure positive drainage and matting over all disturbed areas to pre-demolition conditions.
  • Self-performed 93% of the total cost of the contract

Project Details

Location of Project

MCAS Cherry Point, NC

Awarded

08/14/2018

Completed

03/30/2020

Contract Value

$3,015,821

REFERENCE

NAVFAC
FEAD Public Works Dept.
MCAS Cherry Point
Robby McGee
252.876.8578
Robert.mcgee1@navy.mil
Marc Garland
252.876.8582
Marc.garland@navy.mil

Project Gallery

Committed to an injury-free workplace

We are unwavering in our dedication to ensure zero injuries at every job site. To do this, we follow strict safety guidelines and hire skilled contractors to work on our projects. Staying committed to operating an injury-free workplace is the right choice and the only choice.

Let’s talk about your project.

Only takes a few seconds!