Marshall Space Flight Center, Huntsville, AL
Target completed asbestos abatement and demolition via implosion of this 11-story, 233,519 SF building. We won this project through a lowest price technically acceptable (LPTA) contracting mechanism.
- Developed plans for accident prevention, health and safety, asbestos abatement, demolition, explosive demolitions, engineering surveys, stormwater pollution prevention, site security and site restoration.
- Completed asbestos abatement of 157,560 SF of floor tile and mastic, 245,850 SF of spray-on fireproofing and 24 other miscellaneous types of ACM, disposing of 1,148 tons of asbestos material.
- Recycled 2,250 tons of structural steel, 60,000 pounds of non-ferrous metals, and 25,000 tons of concrete—achieved a 98% waste diversion rate away from landfills.
- Completed 91,462.75 hours of work with ZERO recordable incidents and no lost time. (This is Target and all subcontractors, Target only 41,216.5 hours)
- Project was completed on schedule and success of implosion was highlighted via multiple media, including ABC News, NY Times, YouTube, Instagram, etc.
Project Details
Location of Project
Marshall Space Flight Center,
Huntsville, AL
Awarded
Client Commpany Name
Completed
02/17/23 (Est)
Contract Value
$10,317,000
CONTRACTOR
Megan Vansant
NASA
Marshall Space Flight Center
Huntsville, AL
Megan.r.vansant@nasa.gov
NASA Marshall Space Flight Center
NASA Marshall Space Flight Center
Demo, Building 4200
Timelapse of Completed Project
Project Gallery
Committed to an injury-free workplace
We are unwavering in our dedication to ensure zero injuries at every job site. To do this, we follow strict safety guidelines and hire skilled contractors to work on our projects. Staying committed to operating an injury-free workplace is the right choice and the only choice.